Wiki Markup*Decrease the status of milestones in the main dialogue '\[(Sub-\] ) Group'*
Overview of the milestones of a group company can be found in the _\[(Sub-\] Group_ tab in the _Status_ dialogue. Only in this dialogue you can decrease the status of the _finished_ milestones. Opening of a _finished_ milestone may be reasonable if you have to make some subsequent changes. To decrease the milestone status click on the required milestone. !worddavfa776fffefbea22b53a97180580e509b.png|height=137,width=467! _Fig. 61: Milestones overview in the 'Status' dialogue – '\[Sub-\] Group' tab_ A security query appears when you click on the milestone: !worddav849efd54a726683c0347052e1810a232.png|height=127,width=271! _Fig. 62: Security query when decreasing milestone status_ After that the selected milestone status is decreased. A milestone with the _checked_ status \[blue\] receives the status _finished_ \[green\]. A further click on the milestone decreases its status to _in process_ \[yellow\]. The following figure shows status overview after decreasing the milestone _TRR_ status from _checked_ to _in process{_}: !worddav9523b4378a7bba61ca4a9006926559f2.png|height=137,width=466! _Fig. 63: Decreased milestone_ You can decrease milestone status for individual companies. Please mind that it is not possible to decrease the status of the milestone _Current Taxes Charge_ for members of tax groups and partnerships \[also dependent companies\] if the status of the parent company is _finished{_}. In this case the following error message appears: !worddav08c34d5d872f26e5227a8c8d9caeb9c3.png|height=62,width=646! _Fig. 64: Decrease the status of milestones – Error message because of the higher unit_ *Decrease milestone status by changing master data in the 'Company' dialogue* It is allowed to change data in the _Company_ dialogue \[main dialogue _Master Data{_}\] only if the milestones of the selected company do not have the status _finished{_}. Otherwise, an error message appears: !worddav0c8c95985ec2b3805532e5e52dde0fa8.png|height=60,width=646! _Fig. 65: Change master data in the 'Company' dialogue – Error message since the milestone is 'finished'_ If you still want to change the data in the _Company_ dialogue, decrease the status of the _finished_ milestones first. *Decrease milestone status by changing master data in the 'Countries' dialogue* Data changes \[e.g. tax rates\] in the _Countrie{_}s dialogue applies to all companies that belong to the selected country. If some companies that belong to this country have the milestone status _finished{_}, a security query appears. Upon confirmation the milestone status is changed to _in process{_}. !worddavb289598ff88c4782cbbef40b0fb5f5a6.png|height=173,width=442! _Fig. 66: Security query when changing master data in the 'Countries' dialogue_) Group tab in the Status dialogue. Only in this dialogue you can decrease the status of the finished milestones. Opening of a finished milestone may be reasonable if you have to make some subsequent changes.
To decrease the milestone status click on the required milestone.
Image Added
A security query appears when you click on the milestone:
Image Added
After that the selected milestone status is decreased. A milestone with the checked status (blue) receives the status finished (green). A further click on the milestone decreases its status to in process (yellow).
You can decrease milestone status for individual companies. Please mind that it is not possible to decrease the status of the milestone Current Taxes Charge for members of tax groups and partnerships (also dependent companies) if the status of the parent company is finished. In this case the following error message appears:
Image Added
Decrease milestone status by changing master data in the 'Company' dialogue
It is allowed to change data in the Company dialogue (main dialogue Master Data) only if the milestones of the selected company do not have the status finished. Otherwise, an error message appears.
If you still want to change the data in the Company dialogue, decrease the status of the finished milestones first.
Decrease milestone status by changing master data in the 'Countries' dialogue
Data changes (e.g. tax rates) in the Countries dialogue applies to all companies that belong to the selected country. If some companies that belong to this country have the milestone status finished, a security query appears. Upon confirmation the milestone status is changed to in process.
Image Added